J
Jack
Further to the post a couple of days ago "Calendar Issue" answered by
Julie
I understand by definition :
Project Calendar is the Calendar that shows up under Tools / Options /
Calendar
Task Calendar is the selected in Task Information / Advanced /
Calendar “dedicated cell”
Resource Calendar is selected in the Resource sheet “dedicated cell”.
I am producing a schedule to accompany a proposal for large project.
Different companies will be working different no of hours / day AND
some work Saturday. Some durations are specified in hours and some
durations are specified in days.
In the Gant Chart I enter the resource in the “dedicated resource
cell” and expect the finish date to look at the number of days entered
for duration, then provide a finish date based on the Resources
dedicated calendar. BUT it gives incorrect finish date.
I have tried specifying the Calendar specified for the resource in the
Task Info calendar section as well but still does not give a finish
date as expected. It still it looks at the definition of a day as per
the Tools / Options / Calendar (Project calendar) This is limiting
as the definition of a day should be what the resource will be working
particularly when there is no need for a task calendar (no
restrictions to the days worked as far as the task is concerned)
I am expecting the finish date to align the duration with the
dedicated resources calendar.
I have colleagues who have worked around this for years by fudging and
thereby creating inaccuracies because through trying to achieve the
above they continually fail.
They Give up and either :
• only specify hours , as hours don’t seem to be affected.
• Have all resources work off the project calendars times even though
the resources work different hours / day and no days / week.
To summarize from your response:
Your 1st Paragraph (below) seems to state that the duration entry will
always look at the Tools > Options Calendar to determine days, weeks
and months definition for all resources through the schedule. (This is
very limiting not being able to customize days, weeks and months to
specific resources calendars.)
It is difficult to understand given the reputation of project re
versatility, that to have true “uniqueness” to resources working
times, only hours can be specified in the duration column (not days,
weeks and months)
As per Your 2nd paragraph , I am only interested in using resource
Calendars for all tasks. I enter the resource in the applicable Gant
Chart cell, and up till receiving your response as per the 1st
paragraph expected days, weeks and months to be as per the resource
calendar I specified.
I understand everything you stated in the 3rd paragraph, but as per
your 1st paragraph, it only works correctly when the calendar
referenced is the Project calendar in Tools > Options , (not a
resource calendar with different times) again this is very limiting.
Re your 4th paragraph, I understand but I don’t need to get to the
level of task calendar limitations. On this particular presentation I
am only interested in presenting accurate finish dates over varying
unique resource calendars in days. As per 1st paragraph seems not
possible.
Julie
I understand by definition :
Project Calendar is the Calendar that shows up under Tools / Options /
Calendar
Task Calendar is the selected in Task Information / Advanced /
Calendar “dedicated cell”
Resource Calendar is selected in the Resource sheet “dedicated cell”.
I am producing a schedule to accompany a proposal for large project.
Different companies will be working different no of hours / day AND
some work Saturday. Some durations are specified in hours and some
durations are specified in days.
In the Gant Chart I enter the resource in the “dedicated resource
cell” and expect the finish date to look at the number of days entered
for duration, then provide a finish date based on the Resources
dedicated calendar. BUT it gives incorrect finish date.
I have tried specifying the Calendar specified for the resource in the
Task Info calendar section as well but still does not give a finish
date as expected. It still it looks at the definition of a day as per
the Tools / Options / Calendar (Project calendar) This is limiting
as the definition of a day should be what the resource will be working
particularly when there is no need for a task calendar (no
restrictions to the days worked as far as the task is concerned)
I am expecting the finish date to align the duration with the
dedicated resources calendar.
I have colleagues who have worked around this for years by fudging and
thereby creating inaccuracies because through trying to achieve the
above they continually fail.
They Give up and either :
• only specify hours , as hours don’t seem to be affected.
• Have all resources work off the project calendars times even though
the resources work different hours / day and no days / week.
To summarize from your response:
Your 1st Paragraph (below) seems to state that the duration entry will
always look at the Tools > Options Calendar to determine days, weeks
and months definition for all resources through the schedule. (This is
very limiting not being able to customize days, weeks and months to
specific resources calendars.)
It is difficult to understand given the reputation of project re
versatility, that to have true “uniqueness” to resources working
times, only hours can be specified in the duration column (not days,
weeks and months)
As per Your 2nd paragraph , I am only interested in using resource
Calendars for all tasks. I enter the resource in the applicable Gant
Chart cell, and up till receiving your response as per the 1st
paragraph expected days, weeks and months to be as per the resource
calendar I specified.
I understand everything you stated in the 3rd paragraph, but as per
your 1st paragraph, it only works correctly when the calendar
referenced is the Project calendar in Tools > Options , (not a
resource calendar with different times) again this is very limiting.
Re your 4th paragraph, I understand but I don’t need to get to the
level of task calendar limitations. On this particular presentation I
am only interested in presenting accurate finish dates over varying
unique resource calendars in days. As per 1st paragraph seems not
possible.