Applying work contour changes work...why?

T

TraceyH

I set up a task to be fixed duration and NOT effort driven. I assigned
resources at 50% and 'saved' the change. I went back into the task and
applied a different work contour (default is 'flat') and my work
decreased...I don't understand why this happened. (I have no calendar
assigned to the task and I have not set up resource calendars)
 
J

JulieS

Hi Tracy,

You're question was answered already on 11/7 by Jose Miguel Pineres and
again on 11/8 by Vanita. If you have additional questions, post your follow
up questions to those threads. They have both answered your question fully.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information about
Microsoft Project
 