Assign resource - no work

B

barbara.korte

Hi,

I am having some problem with one schedule in particular.
I create some tasks and assign resource to them.
But when I assign the resource to some tasks, the work remains 0.
If I assign one resource, the duration and the work should match,
shouldn't it?
Don't matter how many resources I assign to a task, it's work don't
change and still is zero (looks like I didn't assign any resource).

Can anyone help me?

Thanks a lot
 
J

JulieS

Hi Barbara,

Is the task a fixed duration task and is scheduled for time marked as
non-working time on the resource's calendar?

Tell us a bit more details:
What is the duration of the task?
Have you modified the resources' calendars with non-working time?
Have you contoured the resource's availability?

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 
S

Steve House

Adiding to Julie's comments. Do you have automatic calculation turned off?
And FYI, duration would equal work only if the resource is assigned 100%.
If you assigned him at 50%, the work would be half the duration, if you
assigned the resource at 200% the work would be double the duration, etc.
 