B
barbara.korte
Hi,
I am having some problem with one schedule in particular.
I create some tasks and assign resource to them.
But when I assign the resource to some tasks, the work remains 0.
If I assign one resource, the duration and the work should match,
shouldn't it?
Don't matter how many resources I assign to a task, it's work don't
change and still is zero (looks like I didn't assign any resource).
Can anyone help me?
Thanks a lot
I am having some problem with one schedule in particular.
I create some tasks and assign resource to them.
But when I assign the resource to some tasks, the work remains 0.
If I assign one resource, the duration and the work should match,
shouldn't it?
Don't matter how many resources I assign to a task, it's work don't
change and still is zero (looks like I didn't assign any resource).
Can anyone help me?
Thanks a lot