Assigning Resources as a group

J

JJHipp

Does anyone know how to assign a group of resources to tasks? I have a set
of resources with everything identical except for work times. I would like
to assign them to multiple tasks. I do not care whom does what, but I do not
want more than one resource working on any one task at a time. Is there a
method other than manually assigning each member of the group individually?
 
R

Rod Gill

If you have a team of writers (for example) and a team leader for them then
one way is to have a resource called Writers Team Leader with max units
representing the number of people in the team. So, 5 in the team = 500% Max
Units.

Now assign all tasks to the team leader and leave the team leader to assign
work in the most efficient way each week.

--

Rod Gill
Project MVP
Visit www.msproject-systems.com for Project Companion Tools and more

NEW!! Project VBA Book now in stock, for details visit:
www.projectvbabook.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top