Yes, you can assign material resources but the scenario you posed in your
question is NOT one of assigning of material resources. A material
resource is an item that is either a: incorporated into the final
deliverable; or b: is consumed by the activity of creating that
deliverable. Your computers doesn't fit into either caregory. If your
project was to install POS terminals in a chain of retail stores and the
10 computers were the actual terminals that you're installing for delivery
to the customer, then they'd be material resources. Fuel to operate a
generator needed to power those 10 computers while people worked with them
in a remote location without regular power would be a material resource
because it's used up by the activity. But in the scenario you're
describing those computers are WORK resources, not materials, as is the
case with most tools, etc. Their availability drives the schedule just
like a computer operator's availability does. Enter them into the resource
list as "Computers", type - work, availability - 2000% to indicate 20
computers in the group. If you need 5 computers for a task, assign
"Computers" to it at 500% and that will leave 15 available for other
things. The name will turn red indicating overallocation if at any time
you have more than 20 computers assigned to use.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
NewsGroup said:
We can assign human resources to a project.
Is it possible to have an accout of the material resources available and
allocate them to projects?
(eg)I have 20 computers available.
I need 10 computers for 1 task.
Is it possible to assign materia; resources as we do for human resources?
Meena.