K
KT
I am having an over allocation problem when I assign a single resource for
multiple task. Say for example, ‘Resource 1’ is assigned to two projects
(Project A & Project B), each takes 20 hours to complete and both start on
the same day. But Project A has a high priority than Project B. So when
assigned, I want ‘Resource 1’ to work on the high priority one first and then
start with the other. But it is not working the way I wanted. When I assign
things in MS Project, it makes ‘Resource 1’ work on both of them together
(more number of hours for the high priority project and less on the other
project) with an over allocation notice. Can somebody help me how to achieve
this? Thanks.
multiple task. Say for example, ‘Resource 1’ is assigned to two projects
(Project A & Project B), each takes 20 hours to complete and both start on
the same day. But Project A has a high priority than Project B. So when
assigned, I want ‘Resource 1’ to work on the high priority one first and then
start with the other. But it is not working the way I wanted. When I assign
things in MS Project, it makes ‘Resource 1’ work on both of them together
(more number of hours for the high priority project and less on the other
project) with an over allocation notice. Can somebody help me how to achieve
this? Thanks.