auto predessecors

B

BorisS

Is there any way that I can (either by a function that exists or a macro
someone may have), once I have sorted a set of tasks (this would not be for
ALL tasks, but just a set that I'd highlight) physically in the view, have
project go in and make sure that the predecessor relationships are in the
order that I have sorted the tasks in.
 
R

Rod Gill

With all the tasks selected, click the unlink icon then the link icon. This
should do what you want.
 