T
Tunamonster
I am finding several cases where I want a task to end at the time another
begins. I have seen on the board here that to do this one copies the Start
date of one task and does a Paste Link into the finish date of another task.
A little clumsy, I think, but so far so good. My understanding is that once
such a link is established then Predecessors for that item are ignored. What
I want, however, is to allow a time lag between two so-linked tasks. I was
trying to figure a way to do with a 3rd milestone task but haven't quite
found it.
Here is the scenario:
We have a heating system that must be replaced for a house project, i.e.
converting from oil to gas. Now, we don't want to go without heat too long in
the house and we want the driving factor to the the gas installation
schedule. However, we will need to get the oil furnace out of the way before
we can put in the gas furnace. If RO is the remove oil task and IG is the
install gas task, then we want to have IG happen asap based on its
predecessors. We want the RO to be driven based on the IG task, but to
precede it. Finally we want to assure a short buffer of around 2-3 days but
not more between the end of RO and begining of IG.
If IG is scheduled to begin 3/20/09 based on its independent predecessors
we'd want the RO task, which takes 2 days for example, to finish 3 days
prior. That is, RO would start 3/15/09, last 2 days until 3/17/09 and then
have a lag/buffer of 3 days until IG is started.
So, how can this be done? I tried creating a task X that is a milestone and
Paste Linked the Begin date of IG to X's Finish date. Next I created a FS
depedency for X to RO with a 3-day lag time. I expected this to work, but in
fact RO is starting and ending more than a week before either X and IG.
begins. I have seen on the board here that to do this one copies the Start
date of one task and does a Paste Link into the finish date of another task.
A little clumsy, I think, but so far so good. My understanding is that once
such a link is established then Predecessors for that item are ignored. What
I want, however, is to allow a time lag between two so-linked tasks. I was
trying to figure a way to do with a 3rd milestone task but haven't quite
found it.
Here is the scenario:
We have a heating system that must be replaced for a house project, i.e.
converting from oil to gas. Now, we don't want to go without heat too long in
the house and we want the driving factor to the the gas installation
schedule. However, we will need to get the oil furnace out of the way before
we can put in the gas furnace. If RO is the remove oil task and IG is the
install gas task, then we want to have IG happen asap based on its
predecessors. We want the RO to be driven based on the IG task, but to
precede it. Finally we want to assure a short buffer of around 2-3 days but
not more between the end of RO and begining of IG.
If IG is scheduled to begin 3/20/09 based on its independent predecessors
we'd want the RO task, which takes 2 days for example, to finish 3 days
prior. That is, RO would start 3/15/09, last 2 days until 3/17/09 and then
have a lag/buffer of 3 days until IG is started.
So, how can this be done? I tried creating a task X that is a milestone and
Paste Linked the Begin date of IG to X's Finish date. Next I created a FS
depedency for X to RO with a 3-day lag time. I expected this to work, but in
fact RO is starting and ending more than a week before either X and IG.