J
Jon Smith
I have a project plan that a project manager sent me that shows the first
baseline of 2800 hours. It correctly totals up the values in Baseline Work
through the project plan.
The client has approved a change request for 100 hours which has been added
as one task. The PM highlights just that task and selects the summary row
option, which both boxes checked, and the Baseline Work total goes to
2562.03, instead of 2900 hours.
I have tried this update with Project 2002 and 2003, gotten the same
results, tried it highlighting the summary row in addition to the new task -
same results
I believe the project manager may have manually adjusted some of the
baseline work fields, but I can't prove that, but don't know if that would
cause the results to vary.
Any suggestions as to why?
baseline of 2800 hours. It correctly totals up the values in Baseline Work
through the project plan.
The client has approved a change request for 100 hours which has been added
as one task. The PM highlights just that task and selects the summary row
option, which both boxes checked, and the Baseline Work total goes to
2562.03, instead of 2900 hours.
I have tried this update with Project 2002 and 2003, gotten the same
results, tried it highlighting the summary row in addition to the new task -
same results
I believe the project manager may have manually adjusted some of the
baseline work fields, but I can't prove that, but don't know if that would
cause the results to vary.
Any suggestions as to why?