Adding a bit to Dave's comment ... a schedule is a dynamic thing - you
create the initial schedule based on the best inofrmation you have
available at the time but as time passes and things evolve, the schedule
continuously changes to reflect new realities. The first task took a week
longer than we had thought it would so the second task has to be
rescheduled to start a week later, that sort of thing. So the scheduled
dates, durations, costs, etc is our best guesses of what will happen based
on the information we now have. The baseline preserves the original
estimates so we always have a constant reference point for measuring
actual and forecast against budget. I like to think of the baseline as
planned while the schedule becomes forecast once work begins.
Saving a baseline, IMHO, is something that should be done only once in the
project's life cycle, as Dave said, typically at Day 0. The only time it
should be re-baselined is when tasks are added or removed so that what
remains of the original plan becomes essentially a new project. Changes
in duration, costs, etc caused by actuals deviated from original estimates
should not give rise to rebaselining. The multiple baselines feature in
Project is an advantage in giving you an audit trail of last minute
changes as the plan is finalized before starting work on the one hand or
changes in the project framework introduced after work begins.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
EmilH said:
Hi.
Can anybody explain me what's the deifference between for example
baseline cost and scheduled cost? If saving baseline takes a snapshot of
the status then I can assume that baseline is planned cost... as
scheduled cost is. What's the point?
Thanks.
Emil.