%
% Complete vs Actual Work
Is there a way to set up a project (2003) where we can see the lastest and
greatest baseline of each section...example: I have a project and have saved
a baseline for the entire thing, then as things or dates shift I save a
different baseline for each section. So for our development section I have 3
baseline saved, and for testing I have 2 baselines saved - how to I get to
see the lastest of both?
Thanks!
Katie
greatest baseline of each section...example: I have a project and have saved
a baseline for the entire thing, then as things or dates shift I save a
different baseline for each section. So for our development section I have 3
baseline saved, and for testing I have 2 baselines saved - how to I get to
see the lastest of both?
Thanks!
Katie