B
Brad
Hi All,
Please tell me if I have this right. If I assign a task to a resource to
start on 2/1/05 and to finish it on 2/5/05, the only way I can track that the
resource did the work between 2/3/05 and 2/8/05 is to create a Baseline and
view the variance?
If I'm using Project Web Access 2003 (with Outlook), will the Actual Start
and Finishes automatically update the cooresponding fields in Project
Professional?
I have a very dynamic project and I'm worried that I would have to create a
new baseline everyday.
Thanks,
Brad
Please tell me if I have this right. If I assign a task to a resource to
start on 2/1/05 and to finish it on 2/5/05, the only way I can track that the
resource did the work between 2/3/05 and 2/8/05 is to create a Baseline and
view the variance?
If I'm using Project Web Access 2003 (with Outlook), will the Actual Start
and Finishes automatically update the cooresponding fields in Project
Professional?
I have a very dynamic project and I'm worried that I would have to create a
new baseline everyday.
Thanks,
Brad