Best practice with tasks duration

F

Filip - beginner

What's the best way to make duration of some tasks. F.e. some task is
gonna take about 2 hrs of real time, but task will be ready for next
day. This soupose to work with project server (PS 2003) when the same
resource is working with few projects in one time. Is it better to make
duratio of this example task 2 hrs or 1 day.

Thansk

Filip

PS. Sorry for my english.
 
M

Mike Glen

Hi Filip,

Always plan for reality. If it takes only 2 hours, then that's the
Duration: 2hours. If you're using Project Server, try posting on the server
newsgroup. Please see FAQ Item: 24. Project Newsgroups. FAQs, companion
products and other useful Project information can be seen at this web
address: http://project.mvps.org/faqs.htm

You might like to have a look at my series on Microsoft Project in the
TechTrax ezine at this site: http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the articles before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 