M
matthewg156
Hi there
I have a best practice question regarding tasks and predecessors.
As an example, say I have the following tasks:
1. Buy ingredients
2. Bake cake
3. Eat cake
4. Cake project completed (milestone)
The tasks obviously have each previous one as its predecessor. Now, fo
the last task, the milestone, each of the tasks 1-3 must be complet
before it can be finished. Do I make the predecessor tasks for task 4 a
tasks 1,2,3? Or is it enough to just put task 3 as the predecessor fo
task 4, as task 3 requires task 2 which requires task 1, etc
I have a best practice question regarding tasks and predecessors.
As an example, say I have the following tasks:
1. Buy ingredients
2. Bake cake
3. Eat cake
4. Cake project completed (milestone)
The tasks obviously have each previous one as its predecessor. Now, fo
the last task, the milestone, each of the tasks 1-3 must be complet
before it can be finished. Do I make the predecessor tasks for task 4 a
tasks 1,2,3? Or is it enough to just put task 3 as the predecessor fo
task 4, as task 3 requires task 2 which requires task 1, etc