K
Kesavan
Hi
I want to plan for the time each resource (assume 2 for now) would spend
on team meetings. The team meeting occurs once a week on Mondays for 1 hr.
What I would like to see in the Resource Usage is 1 hr allocated to each
resource on Mondays.
The following is what I did to achieve the end but I am satisfied with
the solution.
I would greatly appreciate any help on how it is normally done because I
believe this is a very standard requirement for all projects.
To achieve this, I had created a task called "Team Meetings" ( fixed
work). I created a separate calendar with 2 hours per week. All days are
non-working except Mondays.
Assigned resources say R1 and R2 each 50%. THis seems to work fine if both
the resources are 100% dedicated to the project ( max units in Resource
Sheet). If one resource is only 90% on the project, the whole timeline gets
skewy.
Also if one of the resources is on vacation on a particular Monday, the
plan is skewed.
regards
I want to plan for the time each resource (assume 2 for now) would spend
on team meetings. The team meeting occurs once a week on Mondays for 1 hr.
What I would like to see in the Resource Usage is 1 hr allocated to each
resource on Mondays.
The following is what I did to achieve the end but I am satisfied with
the solution.
I would greatly appreciate any help on how it is normally done because I
believe this is a very standard requirement for all projects.
To achieve this, I had created a task called "Team Meetings" ( fixed
work). I created a separate calendar with 2 hours per week. All days are
non-working except Mondays.
Assigned resources say R1 and R2 each 50%. THis seems to work fine if both
the resources are 100% dedicated to the project ( max units in Resource
Sheet). If one resource is only 90% on the project, the whole timeline gets
skewy.
Also if one of the resources is on vacation on a particular Monday, the
plan is skewed.
regards