B
barrymoss
I have a task that starts on the project start date and has no predecessors;
it is a truly independent task. The duration of the task is nine days and we
want to keep the nine days as the duration, but the task is pushing out to
the right for 6 weeks. It's not that the actual task is going to take any
longer to complete, but because of resource constraints it is only getting
pieces done at odd times. Basically, I want to show that it takes nine days
to do this task, as we want to keep this for historical data, but it needs to
show six weeks in the start/finish. Is there a way to do this?
Thanks in advance,
Barry
it is a truly independent task. The duration of the task is nine days and we
want to keep the nine days as the duration, but the task is pushing out to
the right for 6 weeks. It's not that the actual task is going to take any
longer to complete, but because of resource constraints it is only getting
pieces done at odd times. Basically, I want to show that it takes nine days
to do this task, as we want to keep this for historical data, but it needs to
show six weeks in the start/finish. Is there a way to do this?
Thanks in advance,
Barry