A
Arjun M
Friends,
My main tasks and the subtasks have lost links.I am working on a fixed
time line.So rather than the project scheduling i have added the end
date and start dates into my subtasks.But my main taks are not changing
accordingly.As a result my main tasks have different end date and start
date than its sub tasks.I tried to link the taks.But still its not
working.
Please send me suggestions to fix this issue.
Thanks
Arjun M
My main tasks and the subtasks have lost links.I am working on a fixed
time line.So rather than the project scheduling i have added the end
date and start dates into my subtasks.But my main taks are not changing
accordingly.As a result my main tasks have different end date and start
date than its sub tasks.I tried to link the taks.But still its not
working.
Please send me suggestions to fix this issue.
Thanks
Arjun M