Hello everyone!

I have a problem with the Budget checkbox. After creating a Work type
resource, i cannot modify the value (check / uncheck) of the Budget property.
The resources are on a MS Project Server 2007.
Additionally, since Active Dir is synchronized with several Project Groups,
new users are also generated as resource on the Project Server, with disabled
and unchecked Budget checkbox.

Anyone knows how to circumvent, solve the issue?

Thanks in advance
 
D

Dale Howard [MVP]

M1rage --

In the future, please post your Project Server questions in the
microsoft.public.project.server newsgroup, as this newsgroup is dedicated to
the Microsoft Project desktop application only. To answer your question,
when you are creating an enterprise resource in Project Server 2007, you
have the option AT THAT TIME to select the Budget checkbox. After you have
created and saved the enterprise resource in the Enterprise Resource Pool,
you do not have the option to go back and select/deselect the Budget
checkbox. Hope this helps.
 