budgeted hours question

J

jacobite

is there any neat way of finding hour how much work is scheduled to take
place between two future dates? - I can't see any way of doing this without
counting up the hours manually?

cheers

j.
 
J

Jan De Messemaeker

Hi jacobite,

In task usage, right part, right click detail styles, cumulative work, show
Set the appropriate timescale.
Work between dates oiis the difference betsween the two cum figures
HTH
 
J

jacobite

Jan - many thanks. Got you up to 'Work between dates oiis the difference
betsween the two cum figures' - can you be more explicit?

d.
 
J

jacobite

Jan - think I see what you mean now. But is Cum Work not from the start of
the project. What if I only wanted to know between say, 10th Nov 2005 and 14
Jan 2006? - would I need to calculate manually?

cheers

j.
 
J

Jan De Messemaeker

Hi,

That is the difference between cum work (from the start till Nov9) and (from
the start till Jan 2006)
You have to make ONE subtraction manually, sorry.

HTH
 