Calculating duration

S

Sally in Toronto

How do I set MS Project to automatically calculate duration between two dates?

i.e. On a construction site I know which event will trigger the need for
security to be on site. I know which event will cause security to no longer
be required. I don't know how long (duration) I will require security on
site.
I have set the predecessor and I have set the successor, but I am currently
adding days until the interval is filled.

Thanks,

Sally.
 
M

Mike Glen

Hi Sally,

Welcome to this Microsoft Project newsgroup :)

A hammock task should do what you want. Please see FAQ Item: 19. Hammock
Tasks.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
Project MVP
 