S
snetzky
I am running into the usual problem I have with Project in that it
works fine until I start trying to work with resources and it
immediately starts doing stuff I can't explain.
Problem:
I have a Fixed Duration Task with 1 resource at 100% on this task.
The task has a 4 hour duration, which also is the amount of work.
There is a total of 7 of this resource.
All my tasks are fixed duration with the assumption being made that the
contractor will add additional resources if needed.
I am also trying to work with the assumption that a resource will work
on a task until completed.
So if I assign the resource at 100% on this task the resource should be
assigned at 4 hours, right?
4 hour work * 1 unit = 4h duration.
Why then does my duration change to 13.7? If I change my duration back
to 4 hours, Project reduces my resource time to 0 hours.
I have never been able to overcome this problem with Project. It's one
of the reasons many people prefer Primavera or other tools. Primavera
is pricey, but I can at least explain what it's doing when it levels
resources and does the calculations.
Project seems to throw in a bunch of extra calculations but doesn't
explain what they are.
works fine until I start trying to work with resources and it
immediately starts doing stuff I can't explain.
Problem:
I have a Fixed Duration Task with 1 resource at 100% on this task.
The task has a 4 hour duration, which also is the amount of work.
There is a total of 7 of this resource.
All my tasks are fixed duration with the assumption being made that the
contractor will add additional resources if needed.
I am also trying to work with the assumption that a resource will work
on a task until completed.
So if I assign the resource at 100% on this task the resource should be
assigned at 4 hours, right?
4 hour work * 1 unit = 4h duration.
Why then does my duration change to 13.7? If I change my duration back
to 4 hours, Project reduces my resource time to 0 hours.
I have never been able to overcome this problem with Project. It's one
of the reasons many people prefer Primavera or other tools. Primavera
is pricey, but I can at least explain what it's doing when it levels
resources and does the calculations.
Project seems to throw in a bunch of extra calculations but doesn't
explain what they are.