S
snetzky
I'm in agreement about the regressive thing, but I gotta make a living.
<grin>
Bottom line is, I don't have time to do this at the granularity you
suggest, nor do I see it as being particularly useful, given the
structure of the project. As the majority of the tasks don't fit into
a particular task network, they just have to be done sometime between
the start and end of the project, I'm inclined to identify priorities,
which cranes (probably the most critical resource) are needed, and then
let the supervisors on the floor figure out the people resources and
which jobs to work on. The biggest thing here is whether or not they
are getting all of the work done and can finish it all by the deadline.
I have to admit, Project was not my first choice, and this experience
hasn't changed my mind any.
Larry
<grin>
Bottom line is, I don't have time to do this at the granularity you
suggest, nor do I see it as being particularly useful, given the
structure of the project. As the majority of the tasks don't fit into
a particular task network, they just have to be done sometime between
the start and end of the project, I'm inclined to identify priorities,
which cranes (probably the most critical resource) are needed, and then
let the supervisors on the floor figure out the people resources and
which jobs to work on. The biggest thing here is whether or not they
are getting all of the work done and can finish it all by the deadline.
I have to admit, Project was not my first choice, and this experience
hasn't changed my mind any.
Larry