calendar & baseline

K

Kim

I am using MS Project 2002 & need to create a calendar that shows baseline
start & finish, along with some other text fields. However baseline start &
finish appears on the calendar as the start & finish; not what has been
baselined.

Can the baseline start & finish be incoporated into a calendar?
 
C

Chris Marriott

Kim

You cant add fields of information to a calendar view in the same way as a
Gantt chart

You can add fields of information

Right click in the calendar view and select bar styles

Select a bar type e.g. All Tasks

In the text section ... add Baseline Start from the drop down ...if you want
more than one field of information add a comma and select another field ....

This is probably not what you were looking for exactly, but it is the
closest you can get

Hope this helps
--
Regards


Chris Marriott - PMP MCSE MCDBA
UK - EPM Consultant & Trainer
 
R

Rod Gill

Hi,

Don't think you can show baseline in the Calendar View: Use the Tracking
Gantt view for that.
 