K
Kim
I am using MS Project 2002 & need to create a calendar that shows baseline
start & finish, along with some other text fields. However baseline start &
finish appears on the calendar as the start & finish; not what has been
baselined.
Can the baseline start & finish be incoporated into a calendar?
start & finish, along with some other text fields. However baseline start &
finish appears on the calendar as the start & finish; not what has been
baselined.
Can the baseline start & finish be incoporated into a calendar?