Calendar View in Project

A

Aquiles

I've been dealing too hard to get synchronized my Outlook Calendar and my
project file. I realized that If I had a good Calendar view in my project
(such as that one that i had in Outlook Calendar) I would be able to
allocated my tasks better according with my other appointments.

Does anybody know an add-in, or software that I could use to see the project
tasks in a project calendar that looks like the Outlook Calendar, in which I
could take a task and allocate time (in someday at sometime) to perform that
task ?

The Calendar view that my MS Project 2002 has it is very poor, it doesn't
allow me to see my availability to allocate the task and avoid multiple
tasks at the same time.
 
J

Jan De Messemaeker

Hi,

Try this one:

Calendar View
Window, Split
activate the lower pane(click anywhere)
Click Resource Usage in the view bar
Now when you select (a) task(s) in the calendar view you see the resource
load below.
HTH
 

Ask a Question