Hi!
Is it possible to plot summary tasks only with their finish dates on the
calendar view?

Thanks!
Marty
 
G

Gérard Ducouret

Hello Marty,

In the Calendar view, activate the filter "Summary Tasks"
Format / Bar Styles : choose a symbol for the Summary Tasks, and in the
"Field" drop down list, select Name,Finish.

Hope this helps,

Gérard Ducouret
 
M

MartyO

Thanks so much. That worked as you said...however, can I also not have the
duration plotted out on the calendar view and only have the task name appear
on the calendar on it's finish date?
My author's and editor's only want to see their deadline date for that task.
they don't want to see the text listed on every week leading up to that
deadline date.

Thanks so much!
Marty
 
M

Mike Glen

Hi Marty,

If that's your need, then why not create a milestone at the end of the
appropriate tasks and then just show the milestones?

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top