Calendar View

M

Marlon

Does any one know how to organize a calendar view of multi
Projects. When I look at my calendar I often cannot tell
which tasks goes with what Project. Appreciate any
assistance provided.

M
 
K

Kevin Flanagan

The only way I have found success is to make sure you
name your tasks according to the Project name or use a
WBS that is displayed that can differentiate between
projects. i.e. MDX1234.1.1.2 as the WBS code for one
project and then MXF5678.1.1.2 as the other.
 
M

Mike Glen

Hi Marlon,

Welcome to this Microsoft Project newsgroup :)

Open the Calendar view, right click on a bar, Bar Styles.../select All and
in the Text Fields selector type "Project,Name" (without the quotes and no
spaces)/OK.

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on:)

Mike Glen
Project MVP
 
M

Marlon

Mike this seems to work thanks a lot.

marlon
-----Original Message-----
Hi Marlon,

Welcome to this Microsoft Project newsgroup :)

Open the Calendar view, right click on a bar, Bar Styles.../select All and
in the Text Fields selector type "Project,Name" (without the quotes and no
spaces)/OK.

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on:)

Mike Glen
Project MVP




.
 