lthebuilder said:
when i switch to calendar view, may tasks write on top of each other ... is
there a way to fix this?
lthebuilder,
The Calendar view is only useful for projects that a very limited number
of tasks in any given calendar time. It sounds like that is not the case
for your file. In my opinion the Calendar view is essentially worthless
but some users seem to love it, I guess because they are used to seeing
activities on a calendar.
The only "fix" I can suggest is to either not use the Calendar view (the
Gantt Chart view is much more useful for managing a project), or reduce
the number of tasks that occur in a given calendar period. One way to do
that is by developing a filter to isolate a select set of tasks during
the calendar period.
John
Project MVP