We are updating non-working time (holidays and vacations)
in project and resource calendars. I need a report that
shows the holidays. I think there is no standard report I
can use and want to write the VBA code to extract and
report holidays. My problem is that I cannot find the
objects that hold the holiday information. Can someone
point me in the right direction?
With many thanks,
Roland.
 
J

Jan De Messemaeker

Hello,

resource.calendar.period("a day").working
HTH
--
Jan De Messemaeker