M
mikejw
I work on a project that uses MS Project 2003 Standard and we have a
developed a schedule (time only, no resources or cost) based on historical
data (they have done this many times before) where they know a certain number
of people will be needed on the various tasks. They want to add these
resources (people) to get an idea of who and when they will be needed, as
well as seeing where someone might be overallocated. All tasks are currently
in the schedule as "fixed units", non effort-driven.
All tasks are currently on a 6 day/8 hr work week and I've been asked to
change the calendar to a 6 day/10hr day calendar. I've added the resources
to a resource pool all at 100% and need to begin assigning people to tasks
(although not all tasks will have a resource associated with it).
Can someone provide my next steps? My thought is that I should change the
current calendar through "Tools, Change Working Time" to a 6 day/10 hr day
calendar and then change the base calendar on the resource sheet to the same.
Since I want the durations to remain the same throughout the schedule, will
making these changes to the calendars affect my current durations and dates?
Also, would I need to change each task that will have a resource assignment
to a "fixed duration", non effort-driven task?
Any help is greatly appreciated.
developed a schedule (time only, no resources or cost) based on historical
data (they have done this many times before) where they know a certain number
of people will be needed on the various tasks. They want to add these
resources (people) to get an idea of who and when they will be needed, as
well as seeing where someone might be overallocated. All tasks are currently
in the schedule as "fixed units", non effort-driven.
All tasks are currently on a 6 day/8 hr work week and I've been asked to
change the calendar to a 6 day/10hr day calendar. I've added the resources
to a resource pool all at 100% and need to begin assigning people to tasks
(although not all tasks will have a resource associated with it).
Can someone provide my next steps? My thought is that I should change the
current calendar through "Tools, Change Working Time" to a 6 day/10 hr day
calendar and then change the base calendar on the resource sheet to the same.
Since I want the durations to remain the same throughout the schedule, will
making these changes to the calendars affect my current durations and dates?
Also, would I need to change each task that will have a resource assignment
to a "fixed duration", non effort-driven task?
Any help is greatly appreciated.