can a resource close a milestone task in PWA timesheet?

J

Jesse

I have a couple large project schedules with close to 1,000 milestones. I can
assign milestone tasks to resources so they show up on their tasklist. The
time tracking setting on the Project Server is actual work done and work
remaining. The milestone task is 0 work done and 0 work remaining. The only
way I've found to close the task is to add time to work remaining then input
that same time to actual work done. This will change it to 100% and close the
task. However it's no longer a milestone since the duration is not 0. Do you
know a way for a resource to close a milestone task in PWA and have is stay a
milestone task when the project schedule is updated?
 
J

Jan De Messemaeker

Hi,

Sorry but this question belongs in the .Server newsgroiup rather than in the
..developer one.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top