Can I assign an alternative resource in Project 2003 Professional.

T

TP

Is it possible to assign an alternative resource to a task so that Project
can chose which resource to use given the availablity of resources after
applying Resource Levelling?

For example, I have a task that either Dave or Mary can do, but I only need
one of them to carry it out. Normally, I would assign either one or the other
to the task but it would be useful if i could tell Project that either Dave
or Mary could be assigned the task, depending on assignments.
 
M

Mike Glen

Hi TP,

Welcome to this Microsoft Project newsgroup :)

No. Project only delays tasks when levelling, it cannot optimise. You
might do better to assign them as, say, developers, but you cannot then
assign by name - it's one or the other.

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :))

Mike Glen
MS Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top