can MS Project automatically control a resource overallocation?

M

milosnik.boczku

Hi there,

Can MS Project automatically control and prevent a resource
overallocation?

Let's say, I've got 5 tasks assigned to a person "A". Those tasks are
not on the critical path and there is no link between any of them.
Thus, I don't care in which order will be accomplished (I'd like to
avoid defining predecessors), but what is important for me - next task
should start as soon as "A" will be available (not exceed 100%). If
each tasks takes 1 day, and project starts by 01/01: 1st tasks starts
by 01/01, 2nd - 01/02, 3rd 01/03, 4th 01/04 etc. BUT if I will define
3rd task to start by 03/10, tasks 4th should be rescheduled
automaticaly on 01/03.

How can I do that?

Thank you,

MB
 
G

Gérard Ducouret

Hello MB;
Have you tried the leveling feature of Project ?
Tools / Level Resources..../ Level Now

Gérard Ducouret
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top