Briony M
I have a project with some part time staff who I have set to a 2.5 day
callendar.
When I assign a task to them their percentage allocations are double the
other resources. This makes the percentages very misleading. I like to have
my gandt chart with the resource name(s) on the bars. Is there a way of
changing the percentage to the number of hours per resource?
So for e.g a 1w task, instead of saying
John Smith [100%] Sally Jones [20%]
it would say
John Smith [40h] Sally Jones [8h]
Or can you think of another useful way the gandt can be printed out with
this kind of information easily seen.
Thanks
callendar.
When I assign a task to them their percentage allocations are double the
other resources. This makes the percentages very misleading. I like to have
my gandt chart with the resource name(s) on the bars. Is there a way of
changing the percentage to the number of hours per resource?
So for e.g a 1w task, instead of saying
John Smith [100%] Sally Jones [20%]
it would say
John Smith [40h] Sally Jones [8h]
Or can you think of another useful way the gandt can be printed out with
this kind of information easily seen.
Thanks