P
Peter
PWA 2003
Settings:
Under Customize Project Web Access:
Specify the default method for reporting progress on tasks = Hours of
work done per day or week.
Under Lock down defaults:
Force project managers to use the progress reporting method specified
above for all projects = checked
Under Time Period Settings:
Resources should report their hours worked every day = checked
I have one administrative project, and one enterprise project. I can
enter actuals into the administrative project, but for the enterprise
project the actual fields are all yellow. I'm assigned as the only
resource for this task, and it is the only task in the project.
What do I need to do to allow editing of actuals in assigned tasks?
Thanks in advance for any help.
Settings:
Under Customize Project Web Access:
Specify the default method for reporting progress on tasks = Hours of
work done per day or week.
Under Lock down defaults:
Force project managers to use the progress reporting method specified
above for all projects = checked
Under Time Period Settings:
Resources should report their hours worked every day = checked
I have one administrative project, and one enterprise project. I can
enter actuals into the administrative project, but for the enterprise
project the actual fields are all yellow. I'm assigned as the only
resource for this task, and it is the only task in the project.
What do I need to do to allow editing of actuals in assigned tasks?
Thanks in advance for any help.