Cannot see my tasks

G

Grant

I have imported resources and a project into PS 2003. When I sign in as the Project Manager, I can see the project, but do not see any of the tasks assign to the Project Manager. I'm sure I am missing a security concept. Any ideas?
 
G

Gary L. Chefetz \(MVP\)

Grant:

There's more to it than just importing a project, you must also publish it
from the Collaborate menu.

--

Gary L. Chefetz, MVP
"We wrote the book on Project Server
http://www.msprojectexperts.com

-
Grant said:
I have imported resources and a project into PS 2003. When I sign in as
the Project Manager, I can see the project, but do not see any of the tasks
assign to the Project Manager. I'm sure I am missing a security concept.
Any ideas?
 