Cannot update resource calendar

B

Barb K

I am using Enterprise Project Server 2007. I want to enter vacation days for
my resources. When I select Tools --> change working time and select an
individual's calendar I cannot change any days. Is there a permission that I
need to have to do this? Or am I going about this is the correct way?
thanks in advance for assistance.
 
J

Jonathan Sofer

In the future you should submit your server questions to
microsoft.public.project.server newsgroup.

To change the working time of an enterprise resource you have to check out
the enterprise resource in Project Pro and then go to the resource
information screen by double clicking on the resource and then click on the
"Change Working Time..." button under the general tab.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top