J
Jeremy Lloyd
For the life of me I cannot figure out how to change the >default< working
hours from 8am etc to another time - either in the Standard base calendar or
my own calendar.
If you change the hours in the calendar by selecting the days along the top
then Project just changes the days to "Nondefault Working Time" and hashes
out the days in the grid, which makes it impossible to see when you actually
do have a true non-default working time.
Thanks
Jeremy