I face problem with default working days and non working days, While opening
projects by default it needs to thursday friday holiday instead saturday and
sunday.
 
J

Jan De Messemaeker

Hi,

You can change the default for new projects as follows:
Make a T-F calendar in any project
Tools
Organizer
Calendars
Copy "Standard" from your project to global.mpt

Hope this helps,
 