D
Dido
I am very new at project planning and EVM and need your help badly.
Somehow, I was able to put together a project plan that actually worked for
a fixed price contract. The start and end dates were final (well, supposed to
be). However, we got a month of extension and now I need to enter new tasks
(along with assigned work and durations of course), change the project end
date to 10/31/05 (which was 9/30/05 originally) and add more money for the
project. Can someone tell me how to do that?
MS project doesn't even let me change the project end date. I have no clue
what to do. Is it doing that because I am trying to make all these changes on
a baselined project? Is it possible for me to enter the new tasks, extra
money and continue with this project plan? (This is actually what upper
management of my customer wants us to do).
Any ideas will be greatly appreciated.
Thanks!
Somehow, I was able to put together a project plan that actually worked for
a fixed price contract. The start and end dates were final (well, supposed to
be). However, we got a month of extension and now I need to enter new tasks
(along with assigned work and durations of course), change the project end
date to 10/31/05 (which was 9/30/05 originally) and add more money for the
project. Can someone tell me how to do that?
MS project doesn't even let me change the project end date. I have no clue
what to do. Is it doing that because I am trying to make all these changes on
a baselined project? Is it possible for me to enter the new tasks, extra
money and continue with this project plan? (This is actually what upper
management of my customer wants us to do).
Any ideas will be greatly appreciated.
Thanks!