Change resource

R

Rubost So

Hi all,

What is the best way to change the resource of an incomplete task so that
the actual data will not be affected?

Example:
Task A: planned period: 2006.11.01 - 12.20, Resource A:06.11.01 - 06.11.31
Resource B: 06.12.01 - complete (A replaced by B on 06.12.01)

Thanks, Simon
 
D

Dave

Set the remaining work for Resource A to 0 after 06/11/31 and assign B
to it after that date.

There are a number of ways of doing this. You can use the Task Entry
form, the Task Usage View and so on.
 
R

Rubost So

Many thanks Dave.

Dave said:
Set the remaining work for Resource A to 0 after 06/11/31 and assign B
to it after that date.

There are a number of ways of doing this. You can use the Task Entry
form, the Task Usage View and so on.
 
J

Jan De Messemaeker

Hi,

Assign resources button on the toolbar, use Replace from the assign
resources window.
 