chris_culley
Hi Guys,
I've a feeling that there could be a really obvious answer to this that
will have me slapping myself for my own stupidity, but I just can't
find it...
I've just completed an MS Project (MSP 2002) plan for the next 6 months
or so, but noticed that when I set the day length at the beginning, I
only managed to change Mondays to a non default time, and not the
entire week. The default time was 08:00 -> 17:00, but we have more
leisurely 09:00 -> 17:00 days around here.
The upshot is is that I've got all my durations and resources based on
a 9->5 day on Monday, then 8->5 every other day. How can I change all
the days to be 9->5? I've tried fiddling through the Tools->Change
Working Time menu, but can't work out how to change anything other than
a single day at a time...
Any help would be greatfully received!
Thanks in advance,
Chris
I've a feeling that there could be a really obvious answer to this that
will have me slapping myself for my own stupidity, but I just can't
find it...
I've just completed an MS Project (MSP 2002) plan for the next 6 months
or so, but noticed that when I set the day length at the beginning, I
only managed to change Mondays to a non default time, and not the
entire week. The default time was 08:00 -> 17:00, but we have more
leisurely 09:00 -> 17:00 days around here.
The upshot is is that I've got all my durations and resources based on
a 9->5 day on Monday, then 8->5 every other day. How can I change all
the days to be 9->5? I've tried fiddling through the Tools->Change
Working Time menu, but can't work out how to change anything other than
a single day at a time...
Any help would be greatfully received!
Thanks in advance,
Chris