S
sheriz
I'm new to Project and really struggling with durations and dates.
I have a task and four sub-tasks. The final sub-task has a "finish no later
than" date on it because it must be done by April 30. The first sub-task is
linked to a task above. That task was delayed, which will cause my sub-task
in question to run past April 30. How can I clear that "finish no later
than" date, and have it calculate for me? I need to notify my client about
the delay and give them a new finish date.
I know you don't recommend constraints, but it was a client-imposed finish
date.
I have a task and four sub-tasks. The final sub-task has a "finish no later
than" date on it because it must be done by April 30. The first sub-task is
linked to a task above. That task was delayed, which will cause my sub-task
in question to run past April 30. How can I clear that "finish no later
than" date, and have it calculate for me? I need to notify my client about
the delay and give them a new finish date.
I know you don't recommend constraints, but it was a client-imposed finish
date.