(I posted this to the Project Server discussion list but realized that I
should have posted it here in the general questions...)
I have some of my resources tasked at less than 100%. In the resource
information boxes, I have them listed at 85% available units.
However, when they finish a task early, that percentage will change for that
particular task -- it goes down. And when they finish a task late, the
percentage goes up. I would think it would be the other way around. How do
I avoid Project changing this number and have it simply pull in (or push out)
successive tasks?
Thanks!
should have posted it here in the general questions...)
I have some of my resources tasked at less than 100%. In the resource
information boxes, I have them listed at 85% available units.
However, when they finish a task early, that percentage will change for that
particular task -- it goes down. And when they finish a task late, the
percentage goes up. I would think it would be the other way around. How do
I avoid Project changing this number and have it simply pull in (or push out)
successive tasks?
Thanks!