K
karishma
i am working on MSP 2003. i have prepared my planning with standard calender
and default timimgs. but now i would like to change the hours per day and
hrs. pre week. there are around 40 resurces working on the project. i want 20
of them to work in morning shift and other 20 to work in noon shift.
so do i have to change calender to 24-hrs shift? do i have to enter
nondefault time as 5am to 1:30 pm and 2pm to 10:30 pm, both with 1 our break.
so for this i have man-hrs as 40resources*16 hrs=640hrs work. (am i correct
or have i some misinterpritation?
does it going to change the durations for the tasks?
help will be appreciated
and default timimgs. but now i would like to change the hours per day and
hrs. pre week. there are around 40 resurces working on the project. i want 20
of them to work in morning shift and other 20 to work in noon shift.
so do i have to change calender to 24-hrs shift? do i have to enter
nondefault time as 5am to 1:30 pm and 2pm to 10:30 pm, both with 1 our break.
so for this i have man-hrs as 40resources*16 hrs=640hrs work. (am i correct
or have i some misinterpritation?
does it going to change the durations for the tasks?
help will be appreciated