J
John
Hi, I'm very new to Project. I've recently completed a brief (very
brief) class on the software. So I'm reaching out for help.
We are about to start a construction project. The general contractor
gave us a 120 item task list with start dates and durations. There is
some lead and lag time involved from what we can see, When I input the
tasks into Project I used his dates and durations. But, the start has
changed. When I changed the start date in project information, it
didn't make the associated changes to the subsequent tasks. Because I
can't assume the relationships of one task to another, how can I get
the change in start date to roll down to all of the tasks?
Any help would be greatly appreciated. Thanks, John
brief) class on the software. So I'm reaching out for help.
We are about to start a construction project. The general contractor
gave us a 120 item task list with start dates and durations. There is
some lead and lag time involved from what we can see, When I input the
tasks into Project I used his dates and durations. But, the start has
changed. When I changed the start date in project information, it
didn't make the associated changes to the subsequent tasks. Because I
can't assume the relationships of one task to another, how can I get
the change in start date to roll down to all of the tasks?
Any help would be greatly appreciated. Thanks, John