P
prashanth.sharangapani
Dear Friends,
I have the below scenario. I use MPP 2007.
Task A: Resource R1
Task B: Resource R1
Duing the course of my project execution, I need to make a change. R1
needs to work 100% on Task B just for one week (say Nov 17 - 21);
after that week, he goes back and works both Task A and Task B.
My question - how do I indicate that, on Task B, R1 needs to work 100%
only for a particular duration of time?
Thanks,
Prashanth
I have the below scenario. I use MPP 2007.
Task A: Resource R1
Task B: Resource R1
Duing the course of my project execution, I need to make a change. R1
needs to work 100% on Task B just for one week (say Nov 17 - 21);
after that week, he goes back and works both Task A and Task B.
My question - how do I indicate that, on Task B, R1 needs to work 100%
only for a particular duration of time?
Thanks,
Prashanth