P
Priyu Nayak
One of Project Managers was editing a project plan from my computer. So he
was logged into Project Server as me. Since it automaticaly logs in using my
windows account. So now the tasks he edited while he was on my computer are
displayed with me as the owner of the tasks. Even though the project owner is
my colleague. When his resources send updates on the tasks, the emails go out
to me and not him. How do I change the task ownership?
was logged into Project Server as me. Since it automaticaly logs in using my
windows account. So now the tasks he edited while he was on my computer are
displayed with me as the owner of the tasks. Even though the project owner is
my colleague. When his resources send updates on the tasks, the emails go out
to me and not him. How do I change the task ownership?