Changing the Task Owner

P

Priyu Nayak

One of Project Managers was editing a project plan from my computer. So he
was logged into Project Server as me. Since it automaticaly logs in using my
windows account. So now the tasks he edited while he was on my computer are
displayed with me as the owner of the tasks. Even though the project owner is
my colleague. When his resources send updates on the tasks, the emails go out
to me and not him. How do I change the task ownership?
 
M

Mike Glen

Hi Priyu ,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://www.mvps.org/project/.

Mike Glen
Project MVP





Nayak wrote:
:: One of Project Managers was editing a project plan from my computer.
:: So he was logged into Project Server as me. Since it automaticaly
:: logs in using my windows account. So now the tasks he edited while
:: he was on my computer are displayed with me as the owner of the
:: tasks. Even though the project owner is my colleague. When his
:: resources send updates on the tasks, the emails go out to me and not
:: him. How do I change the task ownership?
::
:: --
:: Priyu Nayak
 
D

Dale Howard [MVP]

Priyu --

That guy needs to open the project on his own computer and do the following:

1. Click Collaborate - Publish - All Information
2. Make sure the "Entire project" option is selected at the top of the
dialog
3. Select the "Become the manager for these assignments" option
4. Click OK

Hope this helps.
 