J
John Oakes
I have a task that is estimated at 40h. The Duration and Work are set to
40h. I want to assign a resource to the project with 80% resource
utilization. When I do this, the Duration gets changed to 50h and the Work
remains at 40h. However, I need both to be changed because the resource will
be charging 100% of their time to the project. Is there an easier solution
than changing the Work to the same as Duration to reflect this?
40h. I want to assign a resource to the project with 80% resource
utilization. When I do this, the Duration gets changed to 50h and the Work
remains at 40h. However, I need both to be changed because the resource will
be charging 100% of their time to the project. Is there an easier solution
than changing the Work to the same as Duration to reflect this?