P
Prateek Bhatnagar
Dear All,
iam undergoing a serious problem . I suppose this might be a bug of MS
Project 2003.Actually my problem is that the working time of my organization
has changed and iam not able to change it in global.mpt.
There are basically 3 calendars
1) base calendar
2) project calendar
3) resource calendar
we have some big projects running from a long time and they are scheduled
according to the old calendar.now if i change working time in existing
calendar then it changes time in previous days also and if i introduce a
seperate new calendar then the dates go for toss like anything.iam not able
to edit the working time from a particular date in calendar. for eg before
1st may there were 5 working days with 9hrs/day and after that the time
changed to 6 wortking day in week with 8 hrs /day.Now how to that iam not
able to figure out and i will be thankfull to anybody who can guide me on
this
iam undergoing a serious problem . I suppose this might be a bug of MS
Project 2003.Actually my problem is that the working time of my organization
has changed and iam not able to change it in global.mpt.
There are basically 3 calendars
1) base calendar
2) project calendar
3) resource calendar
we have some big projects running from a long time and they are scheduled
according to the old calendar.now if i change working time in existing
calendar then it changes time in previous days also and if i introduce a
seperate new calendar then the dates go for toss like anything.iam not able
to edit the working time from a particular date in calendar. for eg before
1st may there were 5 working days with 9hrs/day and after that the time
changed to 6 wortking day in week with 8 hrs /day.Now how to that iam not
able to figure out and i will be thankfull to anybody who can guide me on
this