S
Scrufnut
Problem fixed. Thanks for all you help Jan!
Ed
Ed
Jan De Messemaeker said:Hi,
I'm not going to republish the how to do a formula either but maybe we can
get a little closer to a solution.
If you want to see the difference between the start of a task and another
date which exists in an other task, and which may move whenever there is a
plan change, the reply is simple: can't be done with a formula. You need a
VBA procedure to do that.
Formulas only handle data of the task itself, and data on Project level.
For instance, you might set the contract signing date manually as the
project start date - then a formula would be feasible. But should the date
of your signing task move, then you would have to adjust that start date of
the project: manually again.
If either of those solutions may interest you, tell me, I'll give a hand.
Hope this helps,